How to calculate the explosive charge of open pit mine?

First, the amount of charge per hole of shallow hole blasting can be calculated according to the volume formula:
q=kW 3
Or q=kV-kɑHW
In the formula:
Q-load per hole, kg;
K-explosive unit consumption, kg/m 3 ;
V-single hole blasting rock volume.
The total amount of blasting is calculated as follows:
Q=Nq-kV total
In the formula:
Q- total amount of blasting explosives; kg;
N-the total number of blasting holes;
V total - the total amount of blasting of one blasthole; m 3 .
Second, deep hole blasting charge calculation:
(1) Calculation of the cost of a single deep hole blasting fashion:
Under normal circumstances:
Q=qɑHW d
When ɑ≥W d , replace the hole pitch with the chassis resistance line;
Q=qHW d 2
When the step slope angle is less than 55°, the chassis resistance line should be replaced with the minimum resistance line:
Q=qɑHW,
When W d is very different from the segment height H,
Q=qɑW d H 1
In the formula:
H 1 - conversion elevation, m.
H 1 = W d / ( 0.7 ~ 0.8)
When calculating the charge per hole by the above formula, it is also necessary to check with the maximum possible charge G of each hole.
G=g(L-Lr)
In the formula:
G-gun hole may be the maximum charge, kg;
G-the possible charge per metre of the blasthole, kg/m;
L-gun hole length;
Lr-filler length.
Should be satisfied: G ≥ Q is:
G(L-Lr)≥qW d ɑH
(2) Calculation of the volume of multi-row hole blasting fashion:
When multi-row hole blasting, the charge of the first row of holes is calculated as above, and the amount of charge should be increased from the second row.
Q 1 =kqɑbH
In the formula:
Q 1 - the amount of charge per hole in each row after the second row, kg;
K-rock resistance clamping coefficient, when using millisecond blasting, take k=1.0~1.2. When using blasting, take k=1.2~1.5, the second row of holes take the lower limit, and the last row of holes take the upper limit.
(3) Calculation of deep hole charge amount of inclined step
Q'=qWÉ‘L
In the formula:
Q'-the amount of charge per hole of the inclined hole;
Q-explosive unit consumption;
L-oblique hole (excluding ultra deep) length, m.
Tilting deep holes, the ultra-deep part of the dose should be calculated separately:
Q c =ph
In the formula:
Q c - ultra-deep part of the blasthole charge, kg;
P-charge per metre of blasthole, kg / m;
H-super deep.
(4) Subsection charge:
The charge of each segment of the segmented charge is calculated separately:
Q 1 =q 1 É‘W 1 2
Q 2 =q 2 É‘W 2 2
Q 3 =q 3 É‘W 3 2
...
In the formula:
W 1 , W 2 , W 3 - the minimum resistance line of each segment, m.

Small size plastic injection moulding machines specially produce high procison mini Plastic Parts with fast response, stable quality.

It is widely used in food packaging industrial like Plastic Spoons, knifes and forks. 

And also widely sued for stationary industrial like pens. 

Vertification of many year's market application, optimal combination configuration, stable, reliable and durable system with the characteristics of high efficiency, energy saving, low voice and strong power. 

Knife and Fork  (1)


Small Plastic Parts Making Machines

Small Plastic Parts Making Machines,Small Plastic Parts,Small Plastic Parts Mould,Making Injection Molding Machine

Ningbo Tongyong Plastic Machinery Manufacturering Co. Ltd. , https://www.tongyongmachinery.com

Posted on